With a tournament date that could not move, RCP staged the design so construction could start earlier, and staged the build itself to protect the programme and leave time to test the finished stadium. Expanding a live stadium in a residential area meant working through consent variations and keeping neighbours alongside the project, with crowd movement and transport planned to move large numbers in and out without swamping the surrounding streets.
RCP also managed the Rugby World Cup event overlay, the temporary grandstands and the media, hospitality and corporate infrastructure that lifted Eden Park to around 60,000 seats for the tournament and came down once it was over.
Eden Park reopened in 2010 and hosted the Rugby World Cup 2011 final, the biggest event the national stadium had held in more than twenty years.
Awards
Property Council of New Zealand 2011, Excellence in Tourism and Leisure Property