Two aging heritage buildings in central Auckland, brought back to life as offices, retail and hospitality.

HB Central

228 Queen Street

Project Lead

Andre Koolen

Client

Morton Property Group

Service

Management

Location

Auckland

Status

Completed 2023

By 2020 Morton Property Group's two linked buildings on Queen Street had gone tired, their offices vacant or short-term and their seismic rating below a third of the New Building Standard. The family-owned developer weighed demolishing for a fifteen-level tower, and chose instead to keep and reuse the buildings, which date from 1880 and 1914.

That meant removing the seismic risk without losing the character, avoiding the carbon and waste of demolition, and repositioning the property as a boutique home for creative businesses, while finding tenants in a struggling CBD market. Unreinforced masonry, timber floors, murals and old fireplaces had to stay as modern seismic, fire, accessibility and services work went in around them.

RCP managed the project for Morton from initiation through delivery, across design, construction, procurement and contract administration, and coordinated owner, consultants, contractor and tenants. Structuring the work through four building consents and staged completion let the Nike store on Queen Street open six months before the offices were finished, earning income while the rest was still a site.

Some of the strengthening steel was too big to bring in whole and had to be cut down and rebuilt inside. The interior had not been fully stripped before work began, so asbestos, uneven floorplates and hidden structural details surfaced mid-build, and RCP coordinated the redesigns while keeping the old fabric on show. Construction started shortly before Auckland's 2021 lockdown and ran through the 2023 floods and Cyclone Gabrielle.

Completed in 2023, HB Central runs boutique offices above retail and hospitality, the two buildings joined by a central stair through a reopened lightwell. More than 85 percent of the façade and 90 percent of the structure were kept, the strengthening left on show, and the building holds a 5 Star Green Star rating.